Thursday, May 14, 2015

Tejas LCA Mark I Declared "Operationally Deficient"


India's Comptroller and Auditor General (CAG) declared on 8 May that the locally designed Tejas Light Combat Aircraft (LCA) Mk I was "operationally deficient" and its pilots vulnerable even to 7.62 mm rounds fired at the fighter's front end.

In the 63-page report tabled in parliament, Shashi Kant Sharma revealed that the long-delayed LCA Mk I, which obtained its second initial operational clearance (IOC-2) in December 2013, had failed to meet the Indian Air Force's (IAF's) air staff requirements on numerous counts.

It disclosed that to secure IOC-2, the LCA Mk I - under development by the state-run Aeronautical Development Agency (ADA) since 1983 - had to be granted 53 waivers, of which 20 were permanent.

The latter would remain, the CAG said, even after the platform secured its final operational clearance (FOC) scheduled for December 2015. IAF sources said FOC was likely to be deferred.

The LCA Mk I obtained its first IOC from the Centre for Military Airworthiness and Certification in Bangalore in January 2011, only for it to be re-confirmed in 2013 by the definitive IOC-2.

The persistent shortcomings, some of which were still under design, development, and testing, include excessive weight, engine thrust, reduced internal fuel capacity, non-compliance of all-weather operations, non-achievement of single-point defueling fuel system protection, and pilot protection. They restrict the "operational efficiency and survivability of the aircraft, thereby limiting its employability when inducted into IAF squadrons", the report said.

It is also "deficient in electronic warfare (EW) capabilities as specified by the IAF, as the self-protection jammer could not be fitted on the aircraft due to space constraints", the report stated.

Wednesday, February 19, 2014

Tejas Mark II Design Coming out

The Aeronautical Development Agency (ADA) is giving the final touches to the preliminary design of the Light Combat Aircraft (LCA) Tejas Mk-II, scheduled to be completed by the end of March. An official confirmed to Express on Saturday that the detailed design phase of LCA Mk-2 would begin in the second quarter of 2014. A separate project team from ADA and Hindustan Aeronautics Ltd (HAL), dedicated to the upgraded version, is currently undertaking daily reviews to get the first cut of the design out by next month.

The main scope of Tejas Mk-2 programme is to have the engine changed from the current GE F-404 to GE F-414. A development contract for eight engines for the preliminary design phase has already been signed with GE, with the critical design review already been completed at its Boston facility. The Mk-II fighter will have OBOGS (Onboard Oxygen Generating System), which is being developed by Defence Bioengineering and Electromedical Laboratory (DEBEL), a Bangalore-based Defence Research and Development Organisation lab. "Currently, the ground development is over for OBOGS and the systems are undergoing various stages of qualification process," an official who wished not to be named, said.

Thursday, February 13, 2014

India Plans 14 Squadrons of Tejas Fighters to Replace Mig-21 & Mig-27s

India’s own fighter, the Tejas Light Combat Aircraft (LCA), is playing a growing role in protecting Indian airspace. On December 20, when the Tejas was cleared for operational service in the Indian Air Force (IAF), Defence Minister A K Antony declared 200 Tejas fighters would eventually enter combat service. Today, that figure quietly swelled to well above 300, with the government indicating the IAF would have at least 14 Tejas squadrons.

Each IAF combat squadron has 21 fighter aircraft; 14 squadrons add to 294 Tejas fighters. The 21 comprise 16 frontline, single-seat fighters, two twin-seat trainers and three reserve aircraft to make up losses in a war.

In a written statement tabled in the Lok Sabha on Monday, Antony’s deputy, Jitendra Singh, stated, “The MiG-21 and MiG-27 aircrafts of the IAF have already been upgraded and currently equip 14 combat squadrons. These aircraft, however, are planned for being phased out over the next few years and will be replaced by the LCA.”